出口阿尔及利亚承压设备要求
· 压力设备由DGM(矿业总局)监控,该局向工矿部长报告
· 电气或防爆设备由ARH监控,ARH即Autorité De Régulation Des Hydrocarbures(阿尔及利亚国家碳氢化合物管理局)的缩写,隶属于国家能源部的权威检验机构。
制造厂提交“初步档案”批准:通过ARH(电气设备)或DGM(加压设备)
· 批准初步档案后,制造厂必须邀请当局参加工厂试验,或授权第三方检验代理(TPlA)参加工厂试验(FAT)。
· 用工厂测试结果(FAT)填写初步档案,构成最终档案,并将其发送给阿尔及利亚当局批准。(只有在最终档案获得批准后,制造商才能将设备发送至机场)。
· 在设备组装完成后,还计划与制造商一起进行现场测试。
11. Requirements for pressure equipment exported to Algeria
>11.5 summary:
· The pressure equipment is monitored by the DGM(General Directorate of Mines) which reports to the Minister for Industry and Mines and
· the electrical or ATEX equipment is monitored by the ARH
· The manufacturer submits "preliminary dossier" for approval: by ARH (electrical equipment) or the DGM (pressurized equipment)
· After the preliminary dossier is approved, the manufacturer must invite the authorities to attach the factory tests or demand an third part inspection agent (TPLA) to attach the factory tests (fat)
· Complete the preliminary dossier with the factory test results (FAT) to constitute the final dossier and send it for approval by the authorities here in Algeria. (it is only after the approval of the final dossier that Mfr can send the equipment to the airport).
· Onsite tests are also planned with the manufacturer after the equipment has been assembled.